|

Turkey aims to reach $5B wind invest. by year end

With addition of upcoming wind projects, Turkey is close to reaching $5 billion in investments in 2017: Wind Energy head

Ersin Çelik
13:51 - 24/11/2017 Friday
Update: 13:54 - 24/11/2017 Friday
AA
File Photo
File Photo

Turkey plans to achieve around $5 billion in wind energy investments by the end of the year with the help of 1 gigawatt (GW) from Turkish Renewable Energy Resource Zone Project (YEKA) along with finalized wind energy tenders of around 3 GW, according to Turkish Wind Energy Association (TUREB) head on Friday.

TUREB President Mustafa Serdar Ataseven in an exclusive interview with Anadolu Agency said that Turkey's wind energy installed capacity will be boosted through ongoing projects and planned tenders that will be finalized by the end of December.

The next pre-license tender for 2,130 megawatts will be offered over a five-day period starting Monday, Dec. 25 to help generate electricity at competitive prices for Turkish consumers, Ataseven said.

He explained that the projects would take around three to four years for completion after which operations can start to benefit consumers.

"These projects are significant but Turkey can do much better," he asserted adding that Turkey can reach 7 GW of installed capacity by the end of the year.

He advised that investments should continue in order to tap into Turkey’s wind energy potential, which he said is more than double that of the current installed capacity.

According to the General Directorate of Renewable Energy studies, the techno-economic wind energy potential for Turkey is 48 GW but currently, only 11GW of project stock is available.

Nonetheless, progress has been made and Ataseven said the Aegean and Marmara regions have seen an expansion in capacity in the country that is one of the biggest onshore wind markets in Europe.

Turkey has 11GW of wind power stock on hand and has a national target of 20 GW of installed capacity by 2023, he said.

The country's total energy target for 2023 is 100 GW of capacity.

During the three-day period between June 21 and 23, wind energy pre-licenses were put up for tender, and over 200 renewable energy firms attended the rally for a total of 710 megawatts (MW) in wind capacity throughout Turkey.

Turkish Electrical Transmission Company (TEIAS) awarded the tenders for 11 regions in Turkey in the company's office in Ankara during this time.

On Aug. 3, Turkey's first 1,000-megawatt wind tender was realized in Ankara in which a Siemens Gamesa Renewable Energy - Turkerler - Kalyon Energy consortium won the tender offered by YEKA.

The offered price of $3.48 per kilowatt-hour of electricity production clinched Turkey's first 1,000-megawatt wind tender and surpassed the previous record of $10.30 per kilowatt-hour.

#FinanceInvestments
#RenewableWind
#Turkey
6 years ago